Djibouti to Addis Ababa corridor
- Share of Ethiopia's international trade through Djibouti
- Over 90% 1
- Railway length
- 753 km, electrified, single track, standard gauge, 45 stations 1
- Commercial operation began
- 1 January 2018 1
- Freight travel time by rail
- About 10 hours, down from up to 50 hours 1
- Railway ownership
- Ethiopia 75%, Djibouti 25% 1
- Maersk free time, dry import containers, Ethiopia
- 10 days 2
- Maersk demurrage and detention, dry, days 11 to 17
- US$25 a day for 20 ft, US$50 for 40 ft 2
The railway
The Ethio-Djibouti Standard Gauge Railway Company (EDR) runs the line. It is a joint venture owned 75% by Ethiopia and 25% by Djibouti 1. The line replaced a 780 km metre gauge railway built in 1917 1.
The engineering, procurement and construction contract went to CREC and CCECC in 2011. Freight service opened in October 2015 and official commercial operation began on 1 January 2018 1. The cost was US$5.1 billion in 2011 values. Ethiopia and Djibouti financed 30% and the rest came from concessional loans from China Exim Bank, China Development Bank and ICBC 1.
The case study gives a freight capacity of 11.2 million tonnes, rising to 24.9 million tonnes by 2025. It forecast cargo of about 2.3 million tonnes in 2025 1. It says the Chinese contractors operate the line for six years after completion and EDR takes over management from 2024. A summary table in the same study says the contractors operate until 2023 1.
Reported problems on the railway
Shipping line free time and demurrage
Maersk publishes import free time and charges for Ethiopia. Its rates are valid from 29 August 2024 until further notice 2. For dry and non-operating reefer containers the page lists these daily charges after free time 2.
Dwell times reported to UNCTAD
At a UNCTAD workshop on 25 November 2021, the Director General of the Ethiopian Coffee and Tea Authority presented slides stating his own views 6. They said goods take 20 to 30 days to reach Ethiopia from Djibouti port, with port dwell times of 37 days at Djibouti and 59 days at the Modjo dry port 6. The slides gave the railway length as 750 km, against 753 km in the Global Infrastructure Hub study 1,6.
Road charges, bonds and corridor projects
- COMESA harmonised road transit charges are US$10 per 100 km for trucks with more than three axles. Ethiopia is among the countries listed as using them 3.
- Djibouti and Ethiopia are signatories of the COMESA RCTG Carnet regional transit bond 3. In December 2022 COMESA said both had finished preparations and were ready to start operations 4.
- The World Bank approved the Djibouti Regional Economic Corridor Project on 16 December 2021. It aims to improve regional connectivity and logistics efficiency in Djibouti along the southern Djibouti to Addis Ababa corridor and closes on 31 December 2031 5.
Common questions
How long is the Djibouti to Addis Ababa railway?
753 km, according to the Global Infrastructure Hub case study 1.
How long does rail freight take from Djibouti to Addis Ababa?
About 10 hours of travel time, down from up to 50 hours 1.
How many free days do containers to Ethiopia get?
Maersk gives 10 days for dry import containers 2.
Can transit cargo to Ethiopia use the RCTG regional bond?
Ethiopia and Djibouti signed the scheme and were ready to start operations in December 2022, according to COMESA 3,4.
Rules and fees change. Check the official site linked above before you apply or pay. Spotted an error? Email [email protected] with the official link.
Sources
- Global Infrastructure Hub: Addis Ababa to Djibouti Railway case study (30 November 2020)
- Maersk, provider page: Ethiopia import information, free time and demurrage (accessed 20 October 2026)
- COMESA: Trade facilitation programme, road transit charges and RCTG Carnet (accessed 20 October 2026)
- COMESA: Statement by the Secretary General, RCTG Regional Stakeholders Workshop, Victoria Falls (13 to 15 December 2022)
- World Bank: Projects database, Horn of Africa Initiative, Djibouti Regional Economic Corridor Project, P174300 (accessed 20 October 2026)
- UNCTAD: Presentation by Adugna Debella Bote, Ethiopian Coffee and Tea Authority, workshop on landlocked developing countries (25 November 2021)
Related
- Customs transit bonds in East Africa
What a customs transit bond is, how the COMESA RCTG Carnet and the new EACBond work, what they cost and what happens when a bond is called.
- Shipping line container deposits in East Africa
What a shipping line container deposit is, how lines collect and refund it at Mombasa and Dar es Salaam, and what regulators have said.
- Port charges at Mombasa and Dar es Salaam
Selected published container charges at Mombasa and Dar es Salaam, with the date of each tariff and where to read it.
- The Berbera Corridor: Berbera to Ethiopia
Berbera port capacity and ownership, the road to the Ethiopian border, shipping line charges and the status of Ethiopian cargo on the corridor.
- Northern Corridor: Mombasa to Kigali
Road distance, transit times, freight rates, port dwell time and clearance times for cargo moving from Mombasa to Kigali, from Northern Corridor data.